Why the bill of quantities and the drawings stop agreeing at award

The short answer A bill of quantities and a set of shop drawings are two measurements of the same building, taken at two different moments. They will never agree. What matters is whether the difference was visible before the order, and who carries it.

Two measurements of one building, taken at two different moments

A bill of quantities is measured from the tender drawings. The shop drawings are produced after the order, from the same building, at a level of detail nobody had at tender.

Those are two measurements of one object, taken months apart by two parties with two different jobs. They will not agree. The useful question is not whether they agree but whether the gap was visible before the order was placed, and who is carrying it.

What a BOQ cannot count, because nothing has been drawn yet

A BOQ can only measure what is on the drawing in front of the measurer. At tender, much of the building is not yet decided: connection design, bracing arrangement, purlin laps, opening framing, and every dimension that only becomes fixed once a particular structural system is chosen.

So the measurer does the only reasonable thing and measures the building as a shape — tonnage by member type, area by surface — with allowances for the parts that are not there yet. Those allowances are honest, and they are also a guess. The shop drawings replace the guess with an actual member list, and the distance between a guess and a list is the entire argument.

Where the drift actually comes from

Drift is rarely one large omission. It is a set of small, individually defensible measurement conventions, each of which moves the number in the same direction.

Add them up and a building can differ from the tender measurement by a few per cent in mass with nobody having made a mistake. A few per cent of a large frame is not a rounding error. It is a commercial event.

Tonnage is a poor unit for a building

Tonnage measures mass. A project is delivered as pieces: cut, drilled, marked, packed, shipped and erected in a sequence. Two buildings of identical tonnage can differ by hundreds of pieces, and the piece count is what decides fabrication hours, packing volume, container count and erection time.

This is why a tonnage comparison between two offers is so often misleading. The heavier offer is not automatically the more complete one, and the lighter one is not automatically the cheaper one to build. It may simply have counted fewer connections, or measured the secondary members with a thinner allowance.

The register that makes the two reconcilable

The only reliable way to close the gap is to convert both documents into the same unit of account, and that unit is the piece.

A member register — one row per mark, with section, length, quantity and grid position — totals into tonnage at any time, but it can also be checked against the drawing, against the fabrication list, against the packing list and against the erection sequence. A BOQ cannot do any of that, because it was never a list of pieces.

Once the register exists, reconciliation becomes a mechanical operation: sum the register, compare it with the tender measurement, and explain every difference by cause rather than by total. A variance you can attribute is a variation. A variance you cannot attribute is a dispute waiting for a payment milestone.

Why a defined scope holds better than a measured quantity

A measured quantity ties the commercial outcome to a measurement taken before the building was designed. A defined scope ties it to a description of what will be supplied: the structural system, the span and bay grid, the eave height, the crane if there is one, the cladding, the openings, the protection system, the drawings and documents, and the exclusions.

The second form survives detailing, because detailing sits inside the definition instead of outside it. The first does not, because every sheet of shop drawings is an opportunity for the measured quantity to move — and the party holding the measurement is rarely the party doing the detailing.

Neither form removes the need to compare. Both decide where the argument happens: at the order, or at the end.

What to ask before you compare two offers

Two offers that cannot answer these questions in the same language are not comparable, whatever the totals say. The figure at the bottom of a BOQ is a measurement of a drawing. It is not yet a description of a building.

Written by Johnny Joe, who advises owners and project managers in Africa and South America on steel buildings. If a quantity is what worries you on a live project, send the BOQ summary page and the drawing register and I will tell you where the two would separate.

Related: what actually drives the cost of a steel building · what is in a shop drawing set · bay spacing trade-off · how to write a building brief

Next step If you are about to compare offers, send the country, the intended use and the exclusions page. What to send, and how to reach me
Johnny Joe, export engineer at Hebei Hongji Shunda Steel Structure Engineering Co., Ltd.