Choosing a Steel Building Supplier

The short answer A steel building supplier is judged on one thing: whether the drawing that arrives on site can be built by the people standing next to it. Everything else — the website, the photographs, the certificates on the wall — is a claim about that, made before the fact. Buyers who choose well are not better at reading claims. They are better at converting claims into questions with answers that can be checked, and they ask those questions while the answer is still free to change. Choose the supplier whose answers survive being written into the contract.
A shop drawing set open on a table beside steel members
The drawing set is the only document that commits the supplier to a specific building. Everything a buyer asks should end up there.

Most buyers compare suppliers on the things suppliers control: the website, the response speed, the politeness of the quotation, the number of photographs of large halls. Those signals are cheap to produce and they are produced by everyone, which is why they separate almost nobody. The signals that separate suppliers are expensive to produce and therefore rare, and they are almost never volunteered.

This note is the shortlist procedure I would use as a buyer. It assumes the price question has already been asked and answered, because price is the least informative of the available comparisons and the one most buyers start with.

What a supplier is actually being judged on

A supplier is not selling steel. Steel is a commodity with published properties and a market price that moves for reasons no supplier controls. What a supplier sells is a translation: from a client's need, through drawings, into members that fit together on a site eight thousand kilometres away, on a schedule that has no room for a second shipment. The supplier's real product is the accuracy of that translation, and accuracy is what should be judged.

The difference between capacity and control

Capacity is how much steel a plant can move in a month. Control is whether that plant can tell you, on any given day, which member is at which stage. The two are unrelated, and capacity is far easier to photograph. A plant with three production lines and no member tracking will lose a column that a plant with one line and a marking system can account for in a minute. Ask how a specific member is located in the yard, and the answer tells you which of the two you are dealing with.

Why the frame is the wrong thing to compare

Two suppliers quoting the same span will both show a frame, and both frames will look like a frame. The differences live in the numbers behind the drawing: the section sizes, the wind speed the frame was checked against, the design life assumed, the deflection limit at the eave. None of these appear in a rendering and all of them determine whether the building is still serviceable in its twentieth year. Compare section lists, not pictures of frames.

The four questions that cannot be answered after the award

Some questions are cheap to ask before an order and impossible to ask afterwards without renegotiating. They are the four worth spending the first meeting on, because a supplier who answers them badly before the money moves is telling you something the contract cannot fix later.

What wind speed, in km/h, and from what source

Ask for the design wind speed as a number in km/h and ask what it is based on: a national code, a site-specific study, or a figure carried over from a similar project. All three are legitimate answers and they are not equivalent. A supplier who answers with a number and a source is reading the site conditions. A supplier who answers with a range, or with a reference to what is normal, has not read them. Write the number and the source into the specification before the order.

What is not in the quotation

Ask directly what the price excludes, and listen for whether the answer arrives quickly. A supplier who knows their own scope boundary can list the exclusions in one breath: foundations, anchor bolts, erection, insulation, doors, permits, site access. A supplier who hesitates is either unsure of the boundary or hoping it will be discovered late. The exclusion list is a better predictor of the final cost than the price itself.

What the factory visit is standing in for

A factory visit is expensive, slow and often impossible before a first order. What buyers are trying to establish with it is not the size of the building but a small number of process facts that can be established other ways. Understanding what the visit is for makes it possible to get most of the value without making the trip.

Marking, and whether it survives shipping

The single most useful thing to look at in any plant is how members are marked. Marking is the physical link between the drawing and the member, and it is what makes erection possible without the fabricator present. Ask for photographs of marked members in the yard, not of finished members in the workshop. Then ask how the mark is protected through loading, sea freight and unloading. A mark that is painted on and then abraded off in a container is a mark that never existed.

Who signs the inspection, and with what instrument

Every plant inspects. The differences are in what is measured, with what, and who records it. Ask for a completed inspection sheet from a recent project, with the values filled in rather than the headings. Ask what instrument measured the hole gauge and the flange squareness. A plant that can produce a filled sheet is a plant with a system. A plant that produces a blank template is a plant with a form.

Reading a reference list without being fooled

Reference lists are the least reliable document in the trade and the easiest to improve. They are also the only evidence most buyers will ever see of a supplier's actual output, so the skill is not in discarding them but in reading the part that cannot be edited.

Ask about the building that went wrong

Ask a supplier to describe a project where something was fabricated incorrectly and what happened next. This question is hard to prepare for and the answer is unusually informative. A supplier who describes the detection, the replacement, the cost borne and the change made to the process is describing a working quality system. A supplier who has never had a problem is either new, or not looking. Neither is a reason to award.

Specifics that a reference can carry

A reference becomes checkable when it contains span, bay spacing, eave height, floor area, country and year. Those six facts can be corroborated against a photograph, a shipping record or a second conversation. A reference that contains only a client name and a country cannot be checked at all and should be treated as decoration. Ask for the six facts on three projects and see whether the answers stay consistent with each other.

Deciding with incomplete information

No buyer ever has enough information, and the suppliers who insist on more information before quoting are usually the ones who intend to quote carefully. The decision is therefore not about reaching certainty. It is about choosing which uncertainties are acceptable and writing the rest into the order.

Converting an unknown into a clause

Every unresolved question has a contract form. An unclear wind speed becomes a specified value with a stated source. An unclear coating becomes a system with a stated dry film thickness. An unclear loading sequence becomes a drawing requirement. A buyer who converts three unknowns into clauses before the order has removed three arguments from the site phase. Leave them as conversation, and they return as claims.

The supplier who answers in writing

Among suppliers with similar prices and similar plants, choose the one who answers in writing without being pushed. Written answers are slower to produce, they create a record, and they are the only form of answer that can be compared between suppliers. A supplier who will only answer by phone is telling you which of the two they are optimising for. Prefer the one who puts it in the email.

Written by Johnny, who quotes steel buildings for buyers in Africa and South America and who has been on the receiving end of this shortlist for years. If you are comparing suppliers, send me the questions you plan to ask and I will tell you which ones will not get a useful answer.

Related: how to compare two quotes · pre-shipment inspection · how to write a building brief · what is in a shop drawing set

Next step Send the drawing you are pricing and the three suppliers you are considering. I will tell you which of the four questions above each of them has already answered, and which are still open. What to send, and how to reach me — the first read is free.
Delivered reference The buildings we can publish all carry the same six facts: span, bay spacing, eave height, floor area, country and year. A 100 m span food factory in Brazil at 98 m long, 7 m bays and 9,800 m² is the largest of them, and the smallest is a 40 m span logistics warehouse in Burkina Faso at 6 m bays and 2,000 m². Every delivered building is listed with those facts on Projects.

Johnny Joe

Export engineer · Hebei Hongji Shunda Steel Structure Engineering Co., Ltd.

Writes about the decisions that are expensive to change once the drawing is signed — span, eave height, transport envelope, erection sequence. More about me · LinkedIn